Ο/Η (e-mail address removed) ÎγÏαψε:
Once a project is baslined , what is the best way to handle the
following scenarios ?
1) New tasks are to be added
Select a task, then press the Insert button on your keyboard , a new
task will be inserted before the task you had initially selected
2) Reschedule existing tasks(change start dates / dependencies)
To change dependencies you have to break the current dependencies.First
of all select the tasks that you want to change the dependencies then
go to Project Guide > Tasks > Schedule tasks and select the last image
, next to the text "Click to break the link for the selected tasks " .
To change start days remainig work etc go to View > Table and select
Tracking, while the Gant Chart view is selected. You can see the table
next to the gantt has many fields to play with. Experiment with these
fields for a while and you will get the point. It's easy.
Hope that helped , i am a newbie too !!!