Geraint
Hi,
I have put together a simple schedule in project 2002 to track the placement
of material in an underground mine. I have several tasks and each one is
concerned with placing material in individual areas of fixed volume. The
placement is happening at a fixed rate (2000m3/day) and I would like to track
the total of how much material is being placed in a given time period e.g.
per week or month. I would appreciate any pointers or sources of reference.
Thanks