unassiged resource

J

jimdive353

I've never used Project's leveling capability. The other day, a co-worker was
trying to level resources. After Project rearranged the schedule, she notices
there were tasks appearing under an "Unassigned Resource".

This was a total mystery to me. Has anyone encountered this, and what do you
do about it?
 
S

Sarah

They are probably summary tasks, which shouldn't have resources
assigned to them. They also should not have any work assigned, so
leveling should not affect them. Perfectly normal.

SarahK
 
J

jimdive353

Thanks Sarah; I hadn't thought about that. It seemed to me that there were
hours assigned, but I'll check it out.
 