jeremy
Hi
I started this project plan over a week ago - and some of the tasks
are listed with start dates of last week - I imagined when I choose to
"level" the resources it would naturally shift the start date of any
unstarted tasks to a date on or after today. Could anyone tell me how
I would achieve that?
Many thanks