How do I set up a mapping to update actuals for an existing task? In other
words, In project I have a task called “Paint Roomâ€, and a resource named
“Bobâ€. On a spread sheet I have the task name and resource name ("Paint
Room", "Bob") and he performed 8 hours a day on 12/1, 12/2 and 12/3
respectively.
How should this data appear on the excel spread sheet and how would I map
this to the existing task on the project plan so I can update the project
task with the actuals?