I am trying to schedule a project where I will have a person working only a
couple hours over a 2 day period on a particular task, but whenever I put in
two hours for the duration, it changes my start and end date to only one day.
If I change the start and end date to two days, it changes my duration to 16
hours. Is there a way to correct this?