D
Don Epstein
I am a new Project 2003 w/Project Server 2003 user. We frequently perform the
same tasks for network infrastructure projects, such as "migrate user profile
from PC to server", etc. What is the best approach to accumulating and
averaging actual time spent on each instance of this task in order to improve
our task estimation capabilities? Right now we manually capture this
information in an Excel spreadsheet and use that to calculate our averages.
There must be a better way leveraging Project, right? Thanks and Happy
Holidays!
same tasks for network infrastructure projects, such as "migrate user profile
from PC to server", etc. What is the best approach to accumulating and
averaging actual time spent on each instance of this task in order to improve
our task estimation capabilities? Right now we manually capture this
information in an Excel spreadsheet and use that to calculate our averages.
There must be a better way leveraging Project, right? Thanks and Happy
Holidays!