P
patrickk
Context: Project Server 2003 with PWA. We are using the 'Enterprise
Task Number5" custom field to calculate a number for "% Should be
Complete", which we use to give an indication of how much the %
complete of a given task should be on a given day. I've added the
field in the task view where our PWA users update their tasks but no
data is displayed in the field/column in PWA. If I open the project
within Project Pro, I am able to see the data in the field.
I'm not sure if this was the right step to take but in both the
project and the Enterprise Global, I went to Tools... Customize...
Published Fields... and made sure that the custom field is included in
the "Fields in the Tasks View" but the data still doesn't show up in
PWA.
Thanks for the help in advance!
Task Number5" custom field to calculate a number for "% Should be
Complete", which we use to give an indication of how much the %
complete of a given task should be on a given day. I've added the
field in the task view where our PWA users update their tasks but no
data is displayed in the field/column in PWA. If I open the project
within Project Pro, I am able to see the data in the field.
I'm not sure if this was the right step to take but in both the
project and the Enterprise Global, I went to Tools... Customize...
Published Fields... and made sure that the custom field is included in
the "Fields in the Tasks View" but the data still doesn't show up in
PWA.
Thanks for the help in advance!