R
rsmithgi
I am trying to use Project to create cost proposals for Government contracts.
I am trying to use custom cost fields to compute burdened costs. I have run
into an issue that I have not been able to solve. Historically, I have used
several approaches and each has disadvantages:
1. Use already burdened rates for resources. This is a problem because on
some proposals we need to show a breakout of direct and indirect costs on a
task by task basis.
2. Use custom task cost field formulas. This is a problem because I need to
be able to use different formulas for different cost types (e.g direct labor
vs travel).
3. Use custom resource cost field formulas. This is a problem because I
haven't been able to figure out a way for Project to accumulate those costs
for each task that uses resources.
Any guidance will be greatly appreciated.
thanks
Rich
I am trying to use custom cost fields to compute burdened costs. I have run
into an issue that I have not been able to solve. Historically, I have used
several approaches and each has disadvantages:
1. Use already burdened rates for resources. This is a problem because on
some proposals we need to show a breakout of direct and indirect costs on a
task by task basis.
2. Use custom task cost field formulas. This is a problem because I need to
be able to use different formulas for different cost types (e.g direct labor
vs travel).
3. Use custom resource cost field formulas. This is a problem because I
haven't been able to figure out a way for Project to accumulate those costs
for each task that uses resources.
Any guidance will be greatly appreciated.
thanks
Rich