I run multiple filters (8) that are based on the project status date. As the
filters are applied I am prompted to enter the status date each time. Is
there anyway to incorporate the status date as part of the filter? Note: The
status date that I am refering to is listed under the pull down menu;
project/project information/status date.
 
J

Jonathan Sofer

Since [Status Date] is not an available date field in project filters, you
will have to trick the system by creating a custom task level Date field
that simply equals the [Status Date]. Once you define this custom field
then you can create a filter that compares a date against your custom status
date field.

Hope that helps,

Jonathan Sofer
 
C

Craig

Jonathan, thank you for responding so quickly. I will give it a try.

Jonathan Sofer said:
Since [Status Date] is not an available date field in project filters, you
will have to trick the system by creating a custom task level Date field
that simply equals the [Status Date]. Once you define this custom field
then you can create a filter that compares a date against your custom status
date field.

Hope that helps,

Jonathan Sofer


Craig said:
I run multiple filters (8) that are based on the project status date. As
the
filters are applied I am prompted to enter the status date each time. Is
there anyway to incorporate the status date as part of the filter? Note:
The
status date that I am refering to is listed under the pull down menu;
project/project information/status date.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top