Jesse
I can't seem to figure out how to use the status date to adjust tasks....and
I think this is something I can use....so I want to learn...from the project
help file I can see how this should change my tasks.
I went to Project/Options/Calculation and selected
- move end of completed parts after status date back to status date
-- and move start of remaining parts back to status date
- move start of remaining parts before status date forward to status date
-- and move end of completed parts forward to status date
my project start date is 10/31, current date is 11/7, and status date is
1/14. when I enter progress on a task as percent complete the task completed
work or remaining work does not get adjusted around the status date according
to the project/options/calculation settings.
Thoughts to get me started?
I think this is something I can use....so I want to learn...from the project
help file I can see how this should change my tasks.
I went to Project/Options/Calculation and selected
- move end of completed parts after status date back to status date
-- and move start of remaining parts back to status date
- move start of remaining parts before status date forward to status date
-- and move end of completed parts forward to status date
my project start date is 10/31, current date is 11/7, and status date is
1/14. when I enter progress on a task as percent complete the task completed
work or remaining work does not get adjusted around the status date according
to the project/options/calculation settings.
Thoughts to get me started?