S
Sid1962
I have a project where fixed costs for certain summary tasks will vary from
year to year. Is there a trick to assigning these so that I can see the 2006
fixed costs and the 2007 fixed costs? As an alternative, I have created
separate tasks under the summary task called Fixed 2006 and Fixed 2007, and
have assigned the different costs to each of these. I then manipulated the
start dates and durations to make sure they were in the correct years, then
made the fixed costs effective at the start of the project.
Any advice is welcome.
Thanks in advance...
year to year. Is there a trick to assigning these so that I can see the 2006
fixed costs and the 2007 fixed costs? As an alternative, I have created
separate tasks under the summary task called Fixed 2006 and Fixed 2007, and
have assigned the different costs to each of these. I then manipulated the
start dates and durations to make sure they were in the correct years, then
made the fixed costs effective at the start of the project.
Any advice is welcome.
Thanks in advance...