vertical bar graph

P

Project newbie

I've created my plan, now I need to show my results in a vertical bar graph.
The vertical bar graph needs to show each sections work availablity and
burden for each month. I read that there is no way to do stacked graphs in
project, but is there any way to export my data into excel or any other
program that will do vertical bar graphs?
 
J

JackD

I think if you use the "export timescaled data to excel" add-in you should
be able to get the data you need in excel. It will take some clean up once
it is there. Of course, it may not give you everything you need but try it
and then post back for more help.
 
M

Mike Glen

Hi Project newbie,

Welcome to the Microsoft Project newsgroup :)

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
P

Project newbie

Thank you, I will try it and I will let you know if it works. I actually
have another Question to ask. I entered all my tasks and hours that will be
needed to complete my task(AKA-Subtasks). The problem is that my main task
hours are way off. For ex. I have 6 subtasks under my main task and the
hours for the subtasks should all equal 350 but, my main task shows 750 or
higher. When I was entering my data, my main tasks and subtasks were
matching up and then I was messing with views and reports trying to figure
out my vertical bar graphs and that's when I noticed my totals was off. Do
you have any idea what I did to cause this problem and I how do I fix my
totals, since all my fields for the main task are grayed out to correct this
problem. Hope this makes sense. Thank you in advance.
 
P

Project newbie

Great, Your suggestion worked. Thank you. My supervisor will appreciate it.
I'm going to have tons of questions about this project. I hope you can help
me out with them. 1 being; To show available hours vs. work burden in Excel,
I need set up all my subtasks with a regular work week such as 40 hours or is
that by default? 2 being; In Excell I would like to have up to 3 colors to
represent available hours, very important work, and regular work in one
graph. This may not make sense, but lets try these for a starting qestions.
Thank you again!
Project Newbie
 
M

Mike Glen

The Summary task, as it is known, summarises the sub-tasks. The Duration of
a Summary task is the working time from the begining of its first sub-task
to the finish of the end. The only time the Duration of a Summary task will
equal the sum of all its sub-tasks is if they are all linked in a single
chain. However, the Work total should be correct.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top