Viewing committed vs sales pipeline resource allocations

R

Ron Paul

I have two kinds of projects, those that are "committed" (I.e. the contract has been signed) and those that are in the sales pipeline (meaning the contract has not yet been signed). Resources are tentatively committed to sales pipeline tasks.

When I look at resource utilization view, I would like to be able to see that a resource is 80% allocated to committed tasks and 10% allocated to sales pipeline tasks (meaning the contract has not been signed) and 10% free (as an example).

Any suggestions on how to accomplish this?
 
J

Jan De Messemaeker

Hi Ron,
Make a different resource for pipeline tasks, then group both resources to
get a total.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Ron Paul said:
I have two kinds of projects, those that are "committed" (I.e. the
contract has been signed) and those that are in the sales pipeline (meaning
the contract has not yet been signed). Resources are tentatively committed
to sales pipeline tasks.
When I look at resource utilization view, I would like to be able to see
that a resource is 80% allocated to committed tasks and 10% allocated to
sales pipeline tasks (meaning the contract has not been signed) and 10% free
(as an example).
 