Craig
Hi,
I am new to project and have a couple related, basic questions.
1. After setting up a WBS, I see that it is very easy to see which resources
are overallocated. I also can easily see on what days a particular resource
is overallocated. However, I can't seem to figure out how to see to what
tasks a resource is overallocated on a particular day. Any idea how to do
this. For example, if the resource graph shows me that a resource is at 200%
on 8/31/07, how would I be able to view the tasks to which that resource is
assigned on 8/31/07?
2. How am I able to view all tasks that are scheduled to be worked on in a
given time period? For example, if I have a very long WBS, and I want to see
only the tasks that will be worked on during the week of 7/30 to 8/3.
I am new to project and have a couple related, basic questions.
1. After setting up a WBS, I see that it is very easy to see which resources
are overallocated. I also can easily see on what days a particular resource
is overallocated. However, I can't seem to figure out how to see to what
tasks a resource is overallocated on a particular day. Any idea how to do
this. For example, if the resource graph shows me that a resource is at 200%
on 8/31/07, how would I be able to view the tasks to which that resource is
assigned on 8/31/07?
2. How am I able to view all tasks that are scheduled to be worked on in a
given time period? For example, if I have a very long WBS, and I want to see
only the tasks that will be worked on during the week of 7/30 to 8/3.