Hi,
I have a resource named, say Sam who has a management task A & a non-mgmt
task B:
Task A, at 20%, 8 work hour, Start=10/1/Thu, Finish=10/7/Wed, no predecessor
Task B, at 100%, 32 work hours, (no predecessor, therefore it can be started
anytime, preferably to utilize the remaining 80% available time, so that it
too can start on 10/1.)
When I level Sam the schedule puts Task A from 10/1 - 10/7 then pushes Task
B starts from 10/8 - 10/14. I need task A to start 10/1 as well. In the
resource sheet, Sam has 100% unit allocation for the entire duration of the
project - 2 years.
I know that if I put 80% for task B,it will fill in some of those available
time slot but then I have to create another task to fill at 100% after 10/7.
I am basically doing the manual leveling for MS Project - very crude and
cruel I must say if I have to do this for 10+ management tasks & 300
non-management tasks among 10+ resource at wide range of time frames.
I'm sure this is a common situation for many other projects as well. Could
someone PLEASE let me know if you have suggestions/solutions?
Thanks!
Kendra
I have a resource named, say Sam who has a management task A & a non-mgmt
task B:
Task A, at 20%, 8 work hour, Start=10/1/Thu, Finish=10/7/Wed, no predecessor
Task B, at 100%, 32 work hours, (no predecessor, therefore it can be started
anytime, preferably to utilize the remaining 80% available time, so that it
too can start on 10/1.)
When I level Sam the schedule puts Task A from 10/1 - 10/7 then pushes Task
B starts from 10/8 - 10/14. I need task A to start 10/1 as well. In the
resource sheet, Sam has 100% unit allocation for the entire duration of the
project - 2 years.
I know that if I put 80% for task B,it will fill in some of those available
time slot but then I have to create another task to fill at 100% after 10/7.
I am basically doing the manual leveling for MS Project - very crude and
cruel I must say if I have to do this for 10+ management tasks & 300
non-management tasks among 10+ resource at wide range of time frames.
I'm sure this is a common situation for many other projects as well. Could
someone PLEASE let me know if you have suggestions/solutions?
Thanks!