WBS Rollup Problem

J

John Hardy

I have defined WBS levels for my Project activities using a text column.
When I filter on WBS 1.4, the costs roll up for all activities with WBS 1.4,
but not for subordinate (indented) tasks with WBS 1.4.1, or 1.4.2, etc.
Any help appreciated.
 
J

John

John Hardy said:
I have defined WBS levels for my Project activities using a text column.
When I filter on WBS 1.4, the costs roll up for all activities with WBS 1.4,
but not for subordinate (indented) tasks with WBS 1.4.1, or 1.4.2, etc.
Any help appreciated.

John,
I guess I'm a little confused. What do you mean costs don't roll up for
a filtered set? A filter has nothing to do with roll up. What exactly
are you expecting to see?

Just as an aside, is Tools/Options/Calculation tab set for automatic
calculation?

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top