I have a table that is defined by our ERP system and use a macro to pull the
information in from a SQL table via ODBC using an import map. The problem is
that if I look at the SQL table the WBS codes are in sequence but when they
are pulled into Project this seqence is jumbled and resorting on WBS code
does not seem to fix it.

For Example by codes in the SQL table read.
1
1.1
1.1.1
1.1.2
1.1.3
1.1.4
1.2
1.2.1
1.2.2
1.2.3
1.2.4

However when imported they come out as

1
1.1
1.1.1
1.1.3
1.2.2
1.2.3
1.2
1.2.1
1.1.2
1.1.4
1.2.4

which totally mucks up the tasks and sub tasks
Ant ideas ?
 
G

Gérard Ducouret

Hello,
Instead of the WBS code, try to import the Outline Level field

Gérard Ducouret
 
N

Nickb

Gérard Thanks for quick response. However this does not seem to work either.

the structure I am after is like this.

A
B
C
C
C
B
C
C
C

where the B's are subtasks of A and the C's are sub tasks of the B's
to acheive this I have set as suggested the outline levels

1
2
3
3
3
2
3
3
3

The problem is that some tasks at the level 3 get jumbled up into the
different level 2's. I have checked the source table and they are stored in
the correct sequence there and if read sequentually or through the default
index they should be read in correctly.

Do I need to change my Outline level somehow or some how force MS Project to
use the default table index ?