M
Micky Singh
I want to automatically indent tasks (creating subtasks) via a macro or
VBA code based on the task’s WBS number
For example
WBS no. Task name
Project Task 0
1 Task 1
1.1 Task 2
1.1.1 Task 3
1.1.2 Task 4
1.2 Task 5
1.2.1 Task 6
2 Task 7
2.1 Task 8
2.1.1 Task 9
3 Task 10
1, 2 and 3 are all subtasks of project.
1.1 and 1.2 are subtasks of 1
1.1.1 and 1.1.2 are subtasks of 1.1
Thanks
Mike
VBA code based on the task’s WBS number
For example
WBS no. Task name
Project Task 0
1 Task 1
1.1 Task 2
1.1.1 Task 3
1.1.2 Task 4
1.2 Task 5
1.2.1 Task 6
2 Task 7
2.1 Task 8
2.1.1 Task 9
3 Task 10
1, 2 and 3 are all subtasks of project.
1.1 and 1.2 are subtasks of 1
1.1.1 and 1.1.2 are subtasks of 1.1
Thanks
Mike