Week Numbers

P

Philg

I want to construct a schedule but do not want to refer to dates, I know how
to show week numbers onto the gantt chart but is it possible to show week
numbers rather than start and finish dates in columns?

Thank you for any help
Phil
 
J

JulieS

Hi Phil,

In Tools > Options, view tab, you can select the date format noted as W5/2.
It will show the week in the year followed by the day of the week. For
example at task starting today (15 Dec 2005) will show as W50/5 -- the 50th
week, the fifth day of that week.

Hope this helps. Let us know how you get along.

Julie
 