N
NathanG
We're finding that our organization's COST estimates are typically
underestimated. We deliver our projects on-time, but rarely on budget.
We've decided to add a 10% contingency reserve to all of our fixed bid
projects. The challenges are...
1) our paying clients receive a copy of our project plan file in addition to
the Statement of Work
2) the client would be upset if they saw a line item in the project plan for
"contingency", so I need to add 10% to each task
3) the client knows the rates of our resources and can do the math, so the
cost ultimately has to be adjusted via the effort/work
4) the duration of the tasks/deliverables/project should not be impacted by
the 10%
5) I'd prefer not over-allocate resources (i.e. make all tasks fixed
duration and show each resource as doing 8.8 hours of work in an 8 hour day),
as I like to utilize the resource leveling feature
6) this "reserve" will not be refunded to the client if it's not used, at
this time, as a number of our projects have gone over-budget recently
Sorry to be so restrictive, but I wanted to provide a complete set of
"requirements".
Can anyone help me increase the project's cost by 10%?
What are my other options?
underestimated. We deliver our projects on-time, but rarely on budget.
We've decided to add a 10% contingency reserve to all of our fixed bid
projects. The challenges are...
1) our paying clients receive a copy of our project plan file in addition to
the Statement of Work
2) the client would be upset if they saw a line item in the project plan for
"contingency", so I need to add 10% to each task
3) the client knows the rates of our resources and can do the math, so the
cost ultimately has to be adjusted via the effort/work
4) the duration of the tasks/deliverables/project should not be impacted by
the 10%
5) I'd prefer not over-allocate resources (i.e. make all tasks fixed
duration and show each resource as doing 8.8 hours of work in an 8 hour day),
as I like to utilize the resource leveling feature
6) this "reserve" will not be refunded to the client if it's not used, at
this time, as a number of our projects have gone over-budget recently
Sorry to be so restrictive, but I wanted to provide a complete set of
"requirements".
What are my other options?