B
Briony M
AFAIK there seem to be 2 different ways of setting up a resource as part time.
1. is in their personal callendar to set the days or hours they work.
e.g. highlight all thurs and frid as nonworking time for a 3 day week
2. the other is in the resource information box, General tab to set their
availability, e.g. 60% fora 3 day week.
There seem to be pros and cons for each method:
e.g. the second would account for bank holidays correctly (i.e. they would
only get a pro-rata time off for bank holidays) but seems it would be
confusing if they book days off.
The first method (which I have started using) is ok, but if you only want
the resource to work 1 day during a 1 week duration task, instead of setting
the units to 20% as you would usually, you have to set it to 33% (i.e. 33% of
their 3 day week).
Does anyone else have an opinion on which method is more effective?
Many thanks
Briony
1. is in their personal callendar to set the days or hours they work.
e.g. highlight all thurs and frid as nonworking time for a 3 day week
2. the other is in the resource information box, General tab to set their
availability, e.g. 60% fora 3 day week.
There seem to be pros and cons for each method:
e.g. the second would account for bank holidays correctly (i.e. they would
only get a pro-rata time off for bank holidays) but seems it would be
confusing if they book days off.
The first method (which I have started using) is ok, but if you only want
the resource to work 1 day during a 1 week duration task, instead of setting
the units to 20% as you would usually, you have to set it to 33% (i.e. 33% of
their 3 day week).
Does anyone else have an opinion on which method is more effective?
Many thanks
Briony