I am new to project and here is my simple scenario.
I have a task of 2 days which comes to 16 hours, correct?
I also have two resources, one resource is scheduled to work weekends(6
hrs/day) and 2 hours during the work week; the other works just the
week-ends(6 hrs/day).
If I schedule both resources (they start on the sunday), project schedules
each resource with 8 hours and has the both resources working on sunday and
accounts for 12h. On Monday it give resource 1 his final 2 hrs and off the
rest of the week and waits till Saturday to give resource 2 his final 2 hrs.
What I would like to do is start on the Sunday(12h) and allocate resource #1
2h per day till the task is complete. It seems that it should do this
automatically to finish the task as soon as possible.
I guess it is a setting somewhere.
any help or suggestions is greatly appreciated.
andre
I am new to project and here is my simple scenario.
I have a task of 2 days which comes to 16 hours, correct?
I also have two resources, one resource is scheduled to work weekends(6
hrs/day) and 2 hours during the work week; the other works just the
week-ends(6 hrs/day).
If I schedule both resources (they start on the sunday), project schedules
each resource with 8 hours and has the both resources working on sunday and
accounts for 12h. On Monday it give resource 1 his final 2 hrs and off the
rest of the week and waits till Saturday to give resource 2 his final 2 hrs.
What I would like to do is start on the Sunday(12h) and allocate resource #1
2h per day till the task is complete. It seems that it should do this
automatically to finish the task as soon as possible.
I guess it is a setting somewhere.
any help or suggestions is greatly appreciated.
andre