What is the column name for Import\Export of a Project Start

C

chazparks

How do I import a Project Start Date into MS Project? I can't seem to find
the mapping column name.
 
J

Jim Aksel

This should self populate based on the inputs you are making from Excel (with
a default of Today).

You can use the Move Dates wizard to shift the entire project in time once
it has been imported.

The start date is a project property, not a column per se.
try this: activeproject.ProjectStart
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
R

Rob Schneider

The Project Start date is one bit of data, and not a "column". A
"column" in Project is rows of "fields"--thus multiple values.

See the Project Start date in Menu: Project/Project Information, top
left corner of dialog box.

--rms

www.rmschneider.com
 
C

chazparks

I'm using a CSV file that is generated outside of the MS Office products.
Where can I use the Move Dates Wizard from?
 
J

Jim Aksel

This opens a can of worms....
I quoted the incorrect name of the toy.

From within Microsoft Project, you want the "Adjust Dates" feature which is
located on the Analysis Toolbar (View/Toolbars/Analysis). I am sorry for
giving you the incorrect name.

Be careful, if you are using a CSV with dates associated to the tasks
(rather than dependencies), the import wizard is going to lock them down.
That is, once they are in MS Project each task will have a constraint on it:
"Start No Earlier Than"

Make sure all tasks are linked with dependencies (predecessors and
successors) not just keyed dates... keying the dates angers the Scheduling
Gods and precludes Project from doing what it is designed to do because a
keyed date will lock the task to that date.

I am talking without information of your CSV file, if you have dates in it,
make sure you insert the Constraint Type column once you are in Project and
change them all to "As Soon As Possible" and then link your schedule with
Predecessors/Successors.

Let me know if I am off topic.


--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
C

chazparks

Is there away to alter the CSV file and load a MS Project Constraint Type
column with "As soon as Possible"? Is there a recommended finish date
column? I have two serial type numbers for a row but no defined predecessor
and successor type columns. Is there away to use to give a soft adjustment
to the finish date from the CSV so that errors don't happen?
 
J

JulieS

Hi Chazparks,

Pardon me for bumping in. The problem with the constraints that Jim
mentions is when you import data directly into the Start and/or
Finish field in Project. If you import task name data and duration
data, Project's job is to calculate the Start and Finish Field.
While there is a field for Constraint type, you will not be
successful attempting to set a constraint type of ASAP while
importing start or finish dates.

If you want to import date info from the CSV without setting
constraints, consider importing into one of the spare date fields
(Start1, Finish1 or Date1,Date2). You can renamed any field to
"recommended finish date" if you like, but I would let Project drive
the dates through predecessors and successors. If importing
predecessor/successors, you'll need to use TaskIDs (generated by
Project).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top