What the limitation within MS Project 2003?

R

Russ

I'm currently using MS Project 2003 and have a master plan which is made up
of 6 others, all cross linked and accumulating to some 13,000 lines of
activity. I'm now experiencing what can only be considered odd things like
the mix up of task like after removing all filters and sorts etc.

Any offers.
 
J

John

Russ said:
I'm currently using MS Project 2003 and have a master plan which is made up
of 6 others, all cross linked and accumulating to some 13,000 lines of
activity. I'm now experiencing what can only be considered odd things like
the mix up of task like after removing all filters and sorts etc.

Any offers.

Russ,
No need to double post. See my response to your later post. Can you
elaborate more on the problem you are having?

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top