when i add predecessor +12 days it doesnt move it 12 working days

T

trevor

when i add predecessor +12 days it doesnt move it 12 working days as defined
by my working hours, instead it counts with not working saturdays, even though
i defined it to work saturdays,
later, i got it to show the right day, but starting in the middle of the day
 
M

Mike Glen

Hi Trevor,

Welcome to this Microsoft Project newsgroup :)

You will see more clearly what's going on by selecting a Date format that
includes the time - Tools/Options.../View tab. If you have created a new
project calendar with Saturday as a working day, then you need to select it
in Project/Project Information. Check these points first.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
T

Trevor Rabey

Lag is always calculated from the successor's calendar, if there is one, and
from the project calendar otherwise.

--
Trevor Rabey

0407213955
61 8 92729485
Perfect Project Planning
www.perfectproject.com.au
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top