Basically, effort driven means if one person can dig a hole in 8 hours, 2
people can dig the same hole in 4 hours.
Not effort driven is one person can watch concrete dry for 8 hours to make
sure no one steps in itand even if you add a second person, the concrete
won't dry any faster.
That was the easy part.
In MS Project, there are 5 settings:
Fixed Duration, Effort Driven
Fixed Duration, Not Effort Driven
Fixed Units, Effort Driven
Fixed Units, Not Effort Driven
Fixed Work
To complicate things, (a) you can set these setting first, then add
resources, (b) add resources then set the settings, (c) add resources and
then set setting and then add more resources and (d) set settings, add
resources, then change settings.
They all act differently!
So, I assume you have MS Project handy. To best understand what happens is
not reading about it but doing it.
(a) Open Project
(b) Insert Column "Work", "Effort Driven" and "Type"
(c) Add task, just call it "aaaaa" or whatever and make duration 2 days or
whatever
(d) Add a resource, just type in "xxx" or whatever in Resource Name
(e) Look at Work, Effort Driven, and Type
(f) Now, add another resource "yyy" see what happens
(g) Change Effort Driven, and Type, see what happens
(i) Do all the combinations above, including switch the order, and create
additonal tasks
NOTE: If the task has a predecessor, or it there is a constraint on the
task, that would also act differently.
Sorry there wasn't an easy answer! Hope this helps...