When a user updates a task in PWA (i.e., inputs hours worked for a particular
date), where is this reflected in the underlying database?

From reading through the DB documentation, I would have guessed
"MSP_TIMEPHASE_DATA," but that table is empty.

I'm kind of a newbie to project, although not to development. What I'm
ultimately attempting to do is create a list of all active resources who have
NOT made any task updates in the past week, sorted by project, and (also) by
department. If anyone has any further suggestions for me, I would be
appreciative.
 