R
Richard Smith
I have a project that is part way through where I want
leveling to intelligently assign incomplete tasks to
resources but using time in the future such that no
resource can be allocated over 100%. I believe I have all
tasks set to finish "as soon as possible" (e.g. not by a
deadline) so I assume leveliing should push the project out
to ensure no resource is used over 100%.
When I level I am still getting resource utilizations over
100%. What might I be I missing that may be preventing
levelling from resolving the overallocated resources?
I have set all the tasks to be fixed work, finish as soon
as possible,not fixed duration.
Many thanks, any pointers greatly appreciated,
Rihallix
leveling to intelligently assign incomplete tasks to
resources but using time in the future such that no
resource can be allocated over 100%. I believe I have all
tasks set to finish "as soon as possible" (e.g. not by a
deadline) so I assume leveliing should push the project out
to ensure no resource is used over 100%.
When I level I am still getting resource utilizations over
100%. What might I be I missing that may be preventing
levelling from resolving the overallocated resources?
I have set all the tasks to be fixed work, finish as soon
as possible,not fixed duration.
Many thanks, any pointers greatly appreciated,
Rihallix