J
JLP
I am trying to import the finish dates that were updated on a spreadsheet by
the process owners. My WBS code exists on both the project and the
spreadsheet and is the merge key that I am using to update the finish dates.
The mapping exercise seems to work fine, and the dates that I expect to see
appear beside the WBS codes in the mapping wizard, but when I complete the
import, the dates are not updated in project.
How can I get the dates to update from the spreadsheet to the project?
the process owners. My WBS code exists on both the project and the
spreadsheet and is the merge key that I am using to update the finish dates.
The mapping exercise seems to work fine, and the dates that I expect to see
appear beside the WBS codes in the mapping wizard, but when I complete the
import, the dates are not updated in project.
How can I get the dates to update from the spreadsheet to the project?