T
tommcbrny
Hi,
I have a new project plan with tasks that have work specified in hours. I
have resources working on the project with varying Max Units (some 50%
assigned to project, some 75%, some 100%).
In previous projects I've created, assigning a resource with Max Units of
50% to an 8-hour work task resulted in a 2 day duration, which is the desired
result.
In my new project, for some reason, there is no change to the duration when
I assign a resource with less than 100% Max Units as I expect. A four hour
work task, for instance, remains at 1/2d duration even though I assign a 50%
Max Unit resource. An overallocation of the resource results, and the
levelling does not (cannot) resolve the overallocation.
What would cause this?
Thanks,
Tom
I have a new project plan with tasks that have work specified in hours. I
have resources working on the project with varying Max Units (some 50%
assigned to project, some 75%, some 100%).
In previous projects I've created, assigning a resource with Max Units of
50% to an 8-hour work task resulted in a 2 day duration, which is the desired
result.
In my new project, for some reason, there is no change to the duration when
I assign a resource with less than 100% Max Units as I expect. A four hour
work task, for instance, remains at 1/2d duration even though I assign a 50%
Max Unit resource. An overallocation of the resource results, and the
levelling does not (cannot) resolve the overallocation.
What would cause this?
Thanks,
Tom