Ryan Moore
I am seeing a strange issue that has just been pointed out to me by PMs
When they have a project open, this project contains all resources, there is work for all resouces that are assigned to other projects
If a project manager opens another project in Project Professional 2003, the amount of work for the resources in the open project changes. The change is not drastic, usally between plus or minus an hour per day
I know that actual work only displays per open project but why is the total work assigned changing based on the number of open projects
Thanks for any help/input
Ryan
When they have a project open, this project contains all resources, there is work for all resouces that are assigned to other projects
If a project manager opens another project in Project Professional 2003, the amount of work for the resources in the open project changes. The change is not drastic, usally between plus or minus an hour per day
I know that actual work only displays per open project but why is the total work assigned changing based on the number of open projects
Thanks for any help/input
Ryan