A
Andrew
Has Anyone notice with auto leveling off and all the resoucres "max %" is
allocated to 10000 that if you change the work contour when it is on fixed
duration and NOT effort driven it will change the work. if you then fix the
work then the changes the duration? if anyone else has found this problem
please tell me and if there is any way to fix this. I have tryed talking to
Microsoft and have been on hold for over 3 hours on more than 3 occassions.
Kind regards
Andrew Hansen
allocated to 10000 that if you change the work contour when it is on fixed
duration and NOT effort driven it will change the work. if you then fix the
work then the changes the duration? if anyone else has found this problem
please tell me and if there is any way to fix this. I have tryed talking to
Microsoft and have been on hold for over 3 hours on more than 3 occassions.
Kind regards
Andrew Hansen