T
TraceyH
I have created a task as 'fixed duration' and not 'effort driven'. Resource
leveling is 'manual'. I assign individual resources at 30%. The default flat
countour is applied and the calculation is fine. But whenever I go back to
the task and apply a different contour to a resource (tried back load and
late peak) the effort/work changes. I have not created resource calendars or
modified the standard calendar, though I do not have the have the standard
calendar assigned to a task...i can't understand why Project is recalculating
leveling is 'manual'. I assign individual resources at 30%. The default flat
countour is applied and the calculation is fine. But whenever I go back to
the task and apply a different contour to a resource (tried back load and
late peak) the effort/work changes. I have not created resource calendars or
modified the standard calendar, though I do not have the have the standard
calendar assigned to a task...i can't understand why Project is recalculating