Hi!

I am currently working on a large mpp project with some 150 activities
and some 20 resources (only persons/working days). Each of the
resources are categorized as either LOCAL or INTERNATIONAL. I have
tried defining this with either a custom field, a custom outline code
or a group.

Now, what I need to make is a Gantt chart listing for each activity all
of these three columns:
* Work input (total)
* Work input (LOCAL only)
* Work input (INTERNATIONAL only)

Can this be done by a formula or how?

Hope someone can help me.

Best wishes,

Jeppe
 