K
Kahuna
Hi Folks - seems like the most basic of tasks has me challenged!
I need to set every day of the month (every month) as working time. MSP98
seems to calculate the working week as 5 days regardless of what I set in
the Tools>Change Working Time options.
For example: 'Nov 14th 05' to 'Dec 11th 05' should be displayed as 28 days
but in fact it wont even calculate that period instead changing the start
date or end date, and the duration is calculated as 19 days!
How can I get 100% of the month to be used as working time?
Cheers and TIA
I need to set every day of the month (every month) as working time. MSP98
seems to calculate the working week as 5 days regardless of what I set in
the Tools>Change Working Time options.
For example: 'Nov 14th 05' to 'Dec 11th 05' should be displayed as 28 days
but in fact it wont even calculate that period instead changing the start
date or end date, and the duration is calculated as 19 days!
How can I get 100% of the month to be used as working time?
Cheers and TIA