Wrong Durations

D

devagupt

I have a small question.

I have a main project and sub projects with tasks for each sub project
For each sub project , the duration for that particular project is wron
for some reason. It shows for example: Nov 30 3:30 PM Dec 4 2:30 A
as 10.38 days.
We are a 24hr operation . To accomodate this i changed all the tas
information for all tasks to 24 hr in Calander.( is this wrong?)

Since the sub project's durations are wrong , the main project
duration is wrong.

Please help! Thanks in advanc
 
S

Steve House

The 24 hour calendar means that when once a task begins work on it won't
stop, it'll go on 24/7, until the task is done. But the tasks also are
usually broken down to where one task is defined as a package of work done
by one resource resulting in one deliverable. So according to your setup,
if Joe Shmoe is assigned to a 5 day duration task that starts Monday at 8am,
poor Joe would be the only person working on that task and he isn't going to
see his family, have a nap, or even get time for a sandwhich for five
continuous 24-hour days ... he'll be working like a beaver from Monday all
the way through to Saturday morning at 8am without even a single break. Are
you sure this is how you want to schedule your project?
 