D
devagupt
I have a small question.
I have a main project and sub projects with tasks for each sub project
For each sub project , the duration for that particular project is wron
for some reason. It shows for example: Nov 30 3:30 PM Dec 4 2:30 A
as 10.38 days.
We are a 24hr operation . To accomodate this i changed all the tas
information for all tasks to 24 hr in Calander.( is this wrong?)
Since the sub project's durations are wrong , the main project
duration is wrong.
Please help! Thanks in advanc
I have a main project and sub projects with tasks for each sub project
For each sub project , the duration for that particular project is wron
for some reason. It shows for example: Nov 30 3:30 PM Dec 4 2:30 A
as 10.38 days.
We are a 24hr operation . To accomodate this i changed all the tas
information for all tasks to 24 hr in Calander.( is this wrong?)
Since the sub project's durations are wrong , the main project
duration is wrong.
Please help! Thanks in advanc