When i open documents that have been converted from project 98 to 2000 & look
in print preview it is showing the wrong dates(i.e. it should be 2004 whic is
my project timescale and is showing 1984).
The way i've got around this is that if you select all in the timescale
section of the print dialog box then preview this provides you with a
workaround resolve the issue
What i wanted to know is why this is happening? Is it a know problem if so
is there an article to confirm this please?
Thanks
MHD143
in print preview it is showing the wrong dates(i.e. it should be 2004 whic is
my project timescale and is showing 1984).
The way i've got around this is that if you select all in the timescale
section of the print dialog box then preview this provides you with a
workaround resolve the issue
What i wanted to know is why this is happening? Is it a know problem if so
is there an article to confirm this please?
Thanks