Hello,
How can we create the S Curves graph with BCWS, BCWP and ACWP ? I don't find
these values in any "template" of these Blind Reports!
Thanks for your help!
 
J

Jim Aksel

PV=BCWS
EV=BCWP
AC=ACWP

Make sure you are up to date on the service packs and other updates on
P2007. This specific graph is impacted by these.

Also, when you pump out the EV over time graph, set your project status date
far into the future. This allows you to grow PV over time later than "time
now"
--
If this post was helpful, please consider rating it.