2 questions-baseline entire & selected tasks

J

Jack

I've already done a baseline on the entire project.
If I later baseline selected tasks on one of the tasks that I've previously
baselined in the entire project, will that task information overlay the
previously baselined task?
And will I lose the actual work applied to that task?
 
G

Gerard Ducouret

Hello Jack,

Will that task information overlay the previously baselined task?
- The answer is Yes
Will I lose the actual work applied to that task ?
- Hopefully the answer is No !

NB : You can choose how the new baseline data will go upward : to all
summary tasks or into selected summary tasks (2002 version)
Hope this helps,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top