M
Monica
To get a visual of my 1st question, click here:
http://www.startingsource.com/images/question1.jpg
I got this view by clicking on the Task Entry View icon. The duration is 3
hours yet it appears that no one has been scheduled to actually do the work.
I want both resources to work together at the same time for the entire 3
hours. How do I do this?
********
A pic to illustrate my 2nd question:
http://www.startingsource.com/images/question2.jpg
10 hours has been set for the duration but only 5 hours has been given to
actually work on it. Am I missing something? Is there 5 hours somewhere
else? How do I correct this to have 10 full hours given to this task?
Monica
http://www.startingsource.com/images/question1.jpg
I got this view by clicking on the Task Entry View icon. The duration is 3
hours yet it appears that no one has been scheduled to actually do the work.
I want both resources to work together at the same time for the entire 3
hours. How do I do this?
********
A pic to illustrate my 2nd question:
http://www.startingsource.com/images/question2.jpg
10 hours has been set for the duration but only 5 hours has been given to
actually work on it. Am I missing something? Is there 5 hours somewhere
else? How do I correct this to have 10 full hours given to this task?
Monica