G
glpeters
In my schedule there are many more days in my schedule than hours of
required work. for example...
I've allowed 5 days to complete task 1 but the actual hours required to
get the work done is 5. I can't seem to get the duration to ignore the
beginning and ending dates as it always reports 40 hours. This is
happening throughout my plan, where I allow more days to complete a
task and for a particular day may only work on the task for 2 hours.
Thanks for any help.
required work. for example...
I've allowed 5 days to complete task 1 but the actual hours required to
get the work done is 5. I can't seem to get the duration to ignore the
beginning and ending dates as it always reports 40 hours. This is
happening throughout my plan, where I allow more days to complete a
task and for a particular day may only work on the task for 2 hours.
Thanks for any help.