2002 vs. 2003

J

Jodi

I have several files created in 2002 and when I work with them in 2003 the
dates adjust for no reason. I don't know if it is an option that has
changed, but it is not working well. It is not just one file, but all of my
files are doing the same thing. Any ideas? THX
 
J

JackD

We need some more information about what sort of changes you are seeing.
This should not happen.
 
J

Jodi

sorry~
When I have the project in 2002 I have the % complete at 0. If I change
that at all it adjusts all of my completion dates.
 
R

Rod Gill

Was calculation set to automatic in Project 2002? If not, then editing
something in Project 2003 (automatic calculations is on by default) will
force a recalc which would of course change dates.
 