2007 Reports

B

Brendab

I've got a project set up with some tasks assigned to multiple resources. I
can make a report by resource that shows the task for each week that it could
be worked on but I would really like to make a report with tasks that show up
ONLY in the due date week. Does anyone know how to do that? Thanks!!
 
J

Jonathan Sofer

I am assuming this is a view you want in Project Professional?

If so, you can create a resrource filter to apply to a resource usage view.
The filter can be called "Should Finish By" and the conditions should be
"Finish" is less than or equal to "Show assignments that should finish by:"?
And
% Complete is less than 100

When you apply the filter you will have to specify the end date for the
period.

Hope this helps,
Jonathan
 