2008 calendar

J

Jason

hello, i'm setting a new calendar for my resources by copying the standard
and making all holidays a non-working day. I am having to redo all these for
each project. Is there a way i can make the calender for 2008 once and have
it available as a selection for other projects? currently it only shows night
shift,standard, and 24 hours as selections for all.

Thanks in advance,


Jason
 
J

JulieS

Hello Jason,

You can copy the custom calendar to the Global template (Global.mpt) on
your computer by going to
1)Tools > Organizer, select the Calendars tab.
2)Select your custom calendar on the right side of the dialog box
3)Click the copy button to copy your custom calendar to Global.
4)Close the dialog box.

The Global.MPT file (Global template) now has a copy of your custom
calendar. Each project you create from then on you can select your
custom calendar as a base calendar for your resources or as a project or
task calendar.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 