R
RWR
I have two schedules, one set up on a 24 hour calendar(manufacturing), one on
a standard calendar(engineering). When I insert the engineering calendar into
the manufacturing calendar the engineering duration in the duration column
changes (1/3 of engineering duration) The duration is correct in the Gantt
chart. Is there any way to dispay the duration from the engineering schedule
in the duration column of the manufacturing schedule?
a standard calendar(engineering). When I insert the engineering calendar into
the manufacturing calendar the engineering duration in the duration column
changes (1/3 of engineering duration) The duration is correct in the Gantt
chart. Is there any way to dispay the duration from the engineering schedule
in the duration column of the manufacturing schedule?