Hi
I am facing this problem in scheduling a resource whose calendar is a 24Hr
calendar with some exceptions like (one day the resource is working only for
4 hrs)
I create a Task of duration = 3days and effort = 50 hours and then assign
this resource. The resource is allocated as follows:
Day 1 = 33.33 hours (working hours in cal = 24)
Day 2 = 8.33 hrs (working hour in cal = 4 hrs)
Day 3 = 8.33 hrs (working hr in cal = 24 hrs)
Why is the assignment distrbuted like this? (Why not 24 + 4 + 22?)
(%age assignment units on gantt view = 208%, which I can understand is
calculated as Est. Effort / (Duration * Day to hour Conversion setting) .
But still it just seems to be showing peak units and the logic behin
timephased assignment is not clear to me). Pleas help.
Thanks
SM
I am facing this problem in scheduling a resource whose calendar is a 24Hr
calendar with some exceptions like (one day the resource is working only for
4 hrs)
I create a Task of duration = 3days and effort = 50 hours and then assign
this resource. The resource is allocated as follows:
Day 1 = 33.33 hours (working hours in cal = 24)
Day 2 = 8.33 hrs (working hour in cal = 4 hrs)
Day 3 = 8.33 hrs (working hr in cal = 24 hrs)
Why is the assignment distrbuted like this? (Why not 24 + 4 + 22?)
(%age assignment units on gantt view = 208%, which I can understand is
calculated as Est. Effort / (Duration * Day to hour Conversion setting) .
But still it just seems to be showing peak units and the logic behin
timephased assignment is not clear to me). Pleas help.
Thanks
SM