Hello,
I could use some help with my logic. I have created a schedule for a
software test lab that is used by mutiple groups. the lab it self is run
7 days a week 24 hours. The testers work in this lab around the clock.
Let's say group A has the lab for 12 hours and group B has the lab for
the 12 hours. Task A is for group A and Task B is group B. How do I
apply the calendar and the reosurces. Currently I am have task A
starting 10/14/09 and ending on 10/19/2009.
I am using MS Project 2007 and it is not on a project server.
Thanks,
I could use some help with my logic. I have created a schedule for a
software test lab that is used by mutiple groups. the lab it self is run
7 days a week 24 hours. The testers work in this lab around the clock.
Let's say group A has the lab for 12 hours and group B has the lab for
the 12 hours. Task A is for group A and Task B is group B. How do I
apply the calendar and the reosurces. Currently I am have task A
starting 10/14/09 and ending on 10/19/2009.
I am using MS Project 2007 and it is not on a project server.
Thanks,