KevininNH
The base calendar for my project uses an 8 hour workday. I have one task (a
lab test) which will run 24 hours a day. For that task only, I went to Task
Information/Advanced and assigned a 24 hour calendar. I entered a duration
of 48 hours for the task. If I understand correctly, Project should show the
task taking 2 work days (24 hours per workday x 2 days = 48 hours). However,
Project shows it taking 6 work days, which implies that it's still using an 8
hour workday for that task (8 hours a day x 6 days = 48 hours). How do I get
that task to use a 24 hour workday?
Thanks,
Kevin Fredette
Parker Pneutronics
Hollis, NH
lab test) which will run 24 hours a day. For that task only, I went to Task
Information/Advanced and assigned a 24 hour calendar. I entered a duration
of 48 hours for the task. If I understand correctly, Project should show the
task taking 2 work days (24 hours per workday x 2 days = 48 hours). However,
Project shows it taking 6 work days, which implies that it's still using an 8
hour workday for that task (8 hours a day x 6 days = 48 hours). How do I get
that task to use a 24 hour workday?
Thanks,
Kevin Fredette
Parker Pneutronics
Hollis, NH