M
Mark
I have a set of tasks that happen over and over again through out the course
of a project. If one task changes, it should change for each instance where
that task is performed in the project. I'd like to create this task subset
once and then link it through out the project. The problem I run into, is
that it uses the dates and times associated with the subtasks each time I try
to link to it. I'd like it to utilyze the dates from the main project, not
the sub. Is there a way to do this?
of a project. If one task changes, it should change for each instance where
that task is performed in the project. I'd like to create this task subset
once and then link it through out the project. The problem I run into, is
that it uses the dates and times associated with the subtasks each time I try
to link to it. I'd like it to utilyze the dates from the main project, not
the sub. Is there a way to do this?